IT/Controller's Group Project to Retire Hyperion Financial Management
Summary:
Project Kicked Off in 3Q 2013
Wind-Down Liabilities (MTNs and GICs) chosen as pilot
Agile project management methodology utilized
Chosen as leader of Functional Team for Controller's Group
Challenges:
No subledger existed for in-house liability system
Business logic required to derive journals from system reports
Multi-currency portfolio required creation of FX specification to comply with GAAP ASC-830 (FAS 52)
Aggressive timeline - projected April 2014 production rollout
Key Contributions to Project:
Resource management - ensured appropriate accounting resources were made available to meet key deliverables for each sprint
Functional specifications
Developed business logic documentation (ledger activity and FX) and ensured it was in a format which could be readily translated into code by IT team
Provided input into specifications for new reporting to ensure that appropriate analysis and controls would be available post-implementation
Project management
Ongoing assessment of sprint timing with the IT Project Leader
Recommended changes/additions to project map as needed
Resulted additional functionality being added to the application (Buybacks and MTNs at Fair Value)
Results:
Successful move to production environment in April 2014
User acceptance testing and two month parallel reviewed and approved by internal audit with no significant findings
Straight-through processing of journal entries to Computron ledger system
Eliminated the need for IT intervention in monthly close - savings of 2 hours per month
Newly developed reports eliminated the manual updating of over 75 data elements each month
User interface and key components of application to be re-utilized as additional systems are integrated in 2014 (premiums) and 2015 (investments/derivatives)